I am not a big fan of Gantt charts, but currently run my business on ClickUp. I would say that their implementation is not great (sometimes if feels like they go for quantity of features rather than quality).
The specific problems I have with their implementation are
changing dates on tasks do not automatically push out the dependent tasks
There is only F-S (finish-start) dependencies. If you go geeky on Gantt Start-Start, Finish-Finish and other dependencies are important for managing actual vs plan variance
There is no lag implementation (e.g. starts 3 days after the previous task finished).
^^^ these push the Gantt features towards the realms of proper project scheduling tools, but I think a simplistic implementation purely for visualising timelines, whilst useful for comms purposes, are not so useful for functional utility
You don't have permission to do this.
You're going a bit too fast! Take a break and try again in a moment.
Something went wrong! Please reload the page and try again.
I am not a big fan of Gantt charts, but currently run my business on ClickUp. I would say that their implementation is not great (sometimes if feels like they go for quantity of features rather than quality).
The specific problems I have with their implementation are
^^^ these push the Gantt features towards the realms of proper project scheduling tools, but I think a simplistic implementation purely for visualising timelines, whilst useful for comms purposes, are not so useful for functional utility