Comment #⁨3⁩

I am not a big fan of Gantt charts, but currently run my business on ClickUp. I would say that their implementation is not great (sometimes if feels like they go for quantity of features rather than quality).

The specific problems I have with their implementation are

  1. changing dates on tasks do not automatically push out the dependent tasks
  2. There is only F-S (finish-start) dependencies. If you go geeky on Gantt Start-Start, Finish-Finish and other dependencies are important for managing actual vs plan variance
  3. There is no lag implementation (e.g. starts 3 days after the previous task finished).

^^^ these push the Gantt features towards the realms of proper project scheduling tools, but I think a simplistic implementation purely for visualising timelines, whilst useful for comms purposes, are not so useful for functional utility